Rough-Cut Capacity Planning arrives in NetSuite 2026.2

NetSuite 2026.2 brings a significant enhancement to manufacturing through Rough-Cut Capacity Planning (RCCP).

RCCP helps manufacturing planners compare the capacity available at work centres with the capacity required by work orders and planned work orders. It gives planners a mid- to long-term view of critical machine and labour resources before detailed production scheduling begins, helping identify potential overloads and underloads earlier.

Previously, rough-cut capacity planning was available through Advanced Manufacturing with its own configuration requirements. In 2026.2, Oracle has introduced native RCCP into core NetSuite Manufacturing. The feature is built around Manufacturing Routing and Work Centres, alongside Advanced Bill of Materials, so manufacturers using WIP & Routing can now bring capacity planning closer to their existing manufacturing model without relying on Advanced Manufacturing purely for capacity planning.

The practical takeaway is simple: manufacturers can now identify likely capacity constraints earlier, while there is still time to change the plan.

What is Rough-Cut Capacity Planning?

Rough-Cut Capacity Planning is a high-level capacity check that asks one important question:

Do we have enough machine and labour capacity to deliver the production we are planning?

A production plan can look achievable on paper while still placing too much demand on one critical work centre. RCCP provides an earlier view of that risk by comparing required capacity with available capacity over a selected planning period.

What does RCCP show?

NetSuite calculates available capacity from the work centre calendar and its machine and labour capacity resources. The report then compares that capacity with the planned time required by work orders and planned work orders.

RCCP view What it tells you
Machine capacity Available machine capacity versus required machine capacity.
Labour capacity Available labour capacity versus required labour capacity.
Utilisation How heavily each work centre is being used, helping identify overloads and under-utilised resources.
Time buckets Results can be reviewed by day, week or month for a more detailed or longer-term view.

Why is RCCP important for manufacturers?

Capacity constraints are often discovered too late. A business may have enough material, demand and production orders, but still struggle to meet dates because a bottleneck work centre cannot absorb the planned workload.

RCCP moves that conversation earlier in the planning cycle. Instead of waiting for detailed scheduling to reveal the problem, planners can review capacity while the production plan is still flexible.

That can support decisions such as moving production between periods, changing priorities, adding labour, increasing available machine time, or reviewing whether planned demand can realistically be met.

Spot bottlenecks before detailed scheduling

The value of RCCP is particularly clear when one resource is constrained while the rest of the factory has spare capacity.

For example, a manufacturer might have healthy overall capacity but one machining work centre running at 120% utilisation. The problem is not a lack of capacity across the business; it is a constraint concentrated in one part of the production process.

NetSuite lets planners refine results by resource type and utilisation range, making it easier to focus on overloaded or under-utilised work centres. The report can also be drilled into to review the transactions and operations contributing to the requirement.

RCCP and WIP & Routing

The 2026.2 change is particularly relevant for manufacturers already using NetSuite WIP & Routing.

RCCP requires Manufacturing Routing and Work Centres and Advanced Bill of Materials. Manufacturing Routing and Work Centres provides the work centres, resources and routing information that RCCP uses to calculate capacity requirements.

Check that RCCP has been provisioned for your account before enabling it, and confirm the required features and user permissions.

This means the planning chain becomes much more connected:

    • Demand and supply planning establish what needs to be produced.
    • Work orders and planned work orders establish the production requirement.
    • Routings define the operations and work centres involved.
    • RCCP compares the required machine and labour time against available capacity.
    • Planners can address constraints before moving into detailed scheduling.
Five stages from demand and supply planning through work orders, routings and RCCP to addressing capacity constraints.
How RCCP connects production requirements with available capacity.

Does RCCP replace Advanced Manufacturing?

No. RCCP adds a high-level capacity planning capability to core Manufacturing, but Advanced Manufacturing continues to provide broader functionality for advanced manufacturing operations, scheduling and shop-floor processes.

For manufacturers that need to understand whether planned production is likely to overload key work centres, native RCCP may remove the need for Advanced Manufacturing purely to perform rough-cut capacity analysis.

Using planned work orders for longer-term planning

RCCP is not limited to firm work orders. When Supply Planning is used, planned work orders can be included in RCCP through the Include in RCCP option on the relevant Supply Plan Definition.

That is important for mid- to long-term planning because many future production requirements are still planned rather than released as firm work orders. Bringing those planned orders into the capacity view gives planners an earlier indication of future pressure on critical resources.

The importance of accurate manufacturing data

As with any planning tool, RCCP is only as useful as the data behind it.

Manufacturers should review the assumptions that drive available and required capacity, including:

  • Work centre calendars and working time
  • Machine and labour capacity resources
  • Manufacturing routings and operation times
  • Planned work orders and supply planning settings
  • Assembly and BOM data

A capacity report can highlight a problem, but it cannot correct inaccurate master data. For many manufacturers, setting up RCCP is therefore also a good opportunity to review the quality of the underlying manufacturing configuration.

How should manufacturers use RCCP?

RCCP is most valuable when it becomes part of the planning process rather than a report reviewed only when production is already under pressure.

  1. Build the production plan: Establish expected demand and planned production.
  2. Review capacity: Run RCCP across the relevant work centres and planning horizon.
  3. Identify constraints: Focus on overloaded machine or labour resources.
  4. Investigate the drivers: Review the orders and operations contributing to the requirement.
  5. Adjust the plan: Change timing, priorities or available resources where required.
  6. Move to detailed scheduling: Once the broader capacity picture is understood, move into detailed production sequencing.

What does NetSuite 2026.2 mean for manufacturers?

The main change is not simply another manufacturing report. RCCP gives manufacturers a new planning layer between demand and detailed scheduling.

For businesses that currently rely on spreadsheets to estimate capacity, this creates an opportunity to bring more of that analysis into NetSuite. It also gives existing WIP & Routing users a clearer way to connect their production plans with the machine and labour resources required to deliver them.

The questions become much more practical: Which work centres are likely to become bottlenecks? Is the constraint machine time or labour? Which planned orders are driving the overload? And how early can we see the issue?

Frequently Asked Questions

What is Rough-Cut Capacity Planning?

RCCP compares required production capacity with the capacity available at manufacturing work centres. It provides a mid- to long-term view of machine and labour resources before detailed production scheduling.

Is RCCP new in NetSuite 2026.2?

Yes. Oracle lists Rough-Cut Capacity Planning as a new Manufacturing enhancement in NetSuite 2026.2.

Do I need Advanced Manufacturing to use RCCP?

Not for the new native RCCP feature. Oracle lists Manufacturing Routing and Work Center and Advanced Bill of Materials as prerequisites. Advanced Manufacturing remains a separate SuiteApp for broader advanced manufacturing and scheduling capabilities.

Can RCCP include planned work orders?

Yes. Planned work orders generated through Supply Planning can be included when the relevant Supply Plan Definition has Include in RCCP enabled.

Can RCCP identify bottlenecks?

Yes. The report can be refined by resource type and utilisation range so planners can focus on overloaded and under-utilised work centres.

Does RCCP replace detailed production scheduling?

No. RCCP is a high-level capacity planning tool. It helps establish whether the production plan fits available capacity before detailed scheduling takes place.

What should NetSuite manufacturers do now?

NetSuite 2026.2 makes RCCP an important feature to review for manufacturers using WIP & Routing, particularly where capacity planning is currently performed in spreadsheets or separate tools.

Start by checking:

  • Are our work centres accurately configured?
  • Do our routings contain realistic operation times?
  • Are machine and labour resources up to date?
  • Are planned work orders included where they should be?
  • Which work centres are our genuine production constraints?

Getting the answers will help determine whether RCCP can improve the way capacity is planned today, and whether the wider manufacturing configuration needs attention before relying on the new functionality.

Need help optimising NetSuite Manufacturing?

The introduction of RCCP is also a useful opportunity to review the wider manufacturing setup within your NetSuite account.

OneKloudX can support manufacturers with:

  • Manufacturing optimisation: Review WIP, Routing, work centres and production processes.
  • Capacity planning: Assess machine and labour capacity and identify potential bottlenecks.
  • NetSuite 2026.2 readiness: Identify relevant new functionality and opportunities to improve existing processes.
  • Manufacturing configuration: Review routings, BOMs, work centres and planning settings.
  • Ongoing optimisation: Identify opportunities to replace spreadsheets, manual processes or unnecessary customisation.

Ready to understand what NetSuite 2026.2 could change for your manufacturing operation?

Talk to the OneKloudX UK team about your NetSuite manufacturing environment.

Email: info@onekloudx.co.uk
Web: www.onekloudx.co.uk